Planning object
Extension of a production plant by a new building with approx. 8,000 m²

Image source
Hettich-ONI GmbH & Co. KG

The HETTICH group with its headquarters in Kirchlengern is one of the world’s leading manufacturers of furniture fittings. In Exter/Vlotho, HETTICH operates a highly automated assembly plant for the production of high-quality, intelligent furniture technology. In order to implement the HETTICH Group’s growth strategy, a plant structure plan was drawn up, including planning and realisation of an approx. 8,000 m² extension building.

GREAN is a young and innovative team with unconventional ideas. But behind these ideas there is profound know-how. This has been demonstrated time and again in our workshops on strategic location orientation and layout planning.

Jürgen Werner (Managing director Hettich-ONI GmbH & Co. KG)

In the first phase of the project, the current production structures and data, as well as the space allocation at the site, were jointly recorded. On the basis of the ACTUAL recording and the growth scenarios, GREAN and HETTICH developed the future plant structure and various rough layout variants for the site expansion on a workshop basis. Logistics and production areas were modularised and dimensioned. After evaluation and final selection of the preferred variant, the expansion building was realized in only 9 months until the end of 2016.

In detail, the following services were provided:

  • Recording the main value flows

  • Analysis of material flows in the ACTUAL state and in growth scenarios

  • Area recording and segmentation on block layout level

  • Conception of the incoming and outgoing goods

  • Modularisation and dimensioning of production and logistics areas

  • Development, evaluation and selection of coarse layout variants

  • Development of a phased plan for structural implementation

GREAN GmbH



Factory planning

New construction on a greenfield site or expansion of existing buildings - we offer you comprehensive advice and sophisticated planning services for a well conceived factory. For us, this includes basic master and factory structure planning as well as support for your project right through to implementation. Whether new or reorganisation planning - we are experts in factory planning.

Process optimization

In many factories, high inventories, long travel, search or lead times are a major cost factor, which at the same time massively reduces production efficiency. This is what we do: Our customers benefit from well-founded, systematic and analytical consulting. In this way, we work with you to increase the efficiency of your production.

Resource efficiency

High and ever increasing material and energy costs are becoming an efficiency problem in many factories. We systematically investigate where potential is lying dormant and then identify meaningful and economical measures for improvement. In this way we increase the material and energy efficiency in your factory - and at the same time reduce your energy bill.